16365802 - SIM2023.3320.002_CF Hopper Halfcell test

+ New removalRemoval Dashboard
Status
APPROVED
Removed Hours
168.0
hrs
Request details
Requested by
Grant Baldock
Requestor email
-
WO Number
16365802
WO Title
SIM2023.3320.002_CF Hopper Halfcell test
Area
332
Priority
P2
Workgroup
MPV
Reason for removal
Ops unable to clean the area. To be replanned for July shut.
Consequence if not removed
The inspector was unable to make the start of the shut. So his trip has been cancelled.
Removed resources
Scaffold
96.0h
Minprovise Inspector
72.0h
Created: 3/24/2026, 9:08:48 AM
Removed hours
Update the removal resource lines after submission if the removed scope changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
By dion.georgel@greatland.com.au on 3/24/2026, 10:13:50 PM
Completed
Shutdown Coordinator review
No comment recorded.
By john.rowley@greatland.com.au on 3/25/2026, 1:57:05 AM
Completed
Superintendent review
No comment recorded.
By trent.donges@greatland.com.au on 3/25/2026, 2:18:28 AM
Completed
Manager review
No comment recorded.
By ethan.gardiner@greatland.com.au on 3/25/2026, 2:20:47 AM