Company logo
Work Removal Request

15658029 - T1 TA001 Bypass valves Mech Repl

+ New removalRemoval Dashboard
Status
APPROVED
Removed Hours
4.0
hrs
Request details
Requested by
Marty mulhall
Requestor email
martin.mulhall@greatland.com.au
WO Number
15658029
WO Title
T1 TA001 Bypass valves Mech Repl
Area
341
Priority
P2
Workgroup
Mader
Reason for removal
Not enough time or resources to complete job in time that was allocated. Missing parts/ materials to do job is unavailable. Introwest have completed a scope and will prepare for next shut
Consequence if not removed
Will fall behind of schedule
Removed resources
Mech
4.0h
Created: 3/22/2026, 3:21:01 AM
Removed hours
Update the removal resource lines after submission if the removed scope changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
Completed
Shutdown Coordinator review
Replan required. Follow scope attached. Pneumatic control cabinets and lines to be installed by electricians during weekly work. Control Panel stands can be installed during weekly work. So, when it comes to the shutdown Valves can be installed.
Completed
Superintendent review
Not planned correctly. Requires electrical resources, cabinets made off site to be delivered to site, and additional pneumatic hardware avaiable. Pro-West or similar to scope job before they leave March shut, in preparation for next shut. Majority could be completed outside a shut, with just the supply and valve tie in needing to be completed inside shut period
By trent.donges@greatland.com.au on 3/22/2026, 6:06:59 AM
Completed
Manager review
No comment recorded.
By ethan.gardiner@greatland.com.au on 3/22/2026, 6:09:43 AM