Company logo
Work Removal Request

16365180 - 341FC031 Spillage Gutter Mech Install

+ New removalRemoval Dashboard
Status
APPROVED
Removed Hours
152.0
hrs
Request details
Requested by
marty
Requestor email
-
WO Number
16365180
WO Title
341FC031 Spillage Gutter Mech Install
Area
341
Priority
P2
Workgroup
GMRS
Reason for removal
not enough time or labour recourses
Consequence if not removed
won't be done..
Removed resources
Mech fab
24.0h
mech install
48.0h
scaff
32.0h
160 crane
24.0h
rigger
24.0h
Created: 3/24/2026, 6:13:48 AM
Removed hours
Update the removal resource lines after submission if the removed scope changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
By telferfpmmmshutplanners@greatland.com.au on 3/24/2026, 6:29:33 AM
Completed
Shutdown Coordinator review
No comment recorded.
By john.rowley@greatland.com.au on 3/24/2026, 8:27:24 AM
Completed
Superintendent review
Low value WO. Ops need to clean their plant. Gutter will just fill up and end up falling off the tank
By trent.donges@greatland.com.au on 3/24/2026, 8:41:06 AM
Completed
Manager review
No comment recorded.
By ethan.gardiner@greatland.com.au on 3/24/2026, 8:53:13 AM