Work Removal Request
15779949 - T1 SAG Mill Motor Supports - Lower
+ New removal
Removal Dashboard
Status
SUPER_REVIEW
Removed Hours
26.5
hrs
Request details
Requested by
Ivan
Requestor email
ivan.wong@greatland.com.au
WO Number
15779949
WO Title
T1 SAG Mill Motor Supports - Lower
Area
332ML001
Priority
P2
Workgroup
MPV
Reason for removal
Work could not be completed due to reline occuring. Once reline was complete, the work group scheduled to do this work had flown off site.
Consequence if not removed
Push to next shut.
Removed resources
MPV Civil
26.5h
Created: 3/25/2026, 1:02:21 AM
Removed hours
Update the removal resource lines after submission if the removed scope changes.
+ Add resource
Remove
Save removed hours
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
By telferfpmmmshutplanners@greatland.com.au on 3/25/2026, 2:46:46 AM
Completed
Shutdown Coordinator review
No comment recorded.
By john.rowley@greatland.com.au on 3/25/2026, 5:40:56 AM
Completed
Superintendent review
No comment recorded.
Email sent
Manager review
No comment recorded.
Waiting