WR13109371 - 332HO031 Remove Steel Plate

+ New requestDashboard
Status
COMPLETED
Progress
100%
Hours (Planned)
4.0
hrs
Hours (Done)
4.0
hrs
Request details
Requested by
Ivan Wong
Requestor email
ivan.wong@greatland.com.au
WO Number
WR13109371
WO Title
332HO031 Remove Steel Plate
Area
331HO031
Priority
High
Workgroup
TMS Mader MPV
Reason
Remove steel plate from inside hopper and fill voids with wearmax and rubber repairs. Risk of steel plate dislosdging and blocking CFP.
Consequence
Downtime from steel plate blocking CFP feed. Potential for getting stuck in pipe/pump causing damage.
Resources
Mech
4.0h
Created: 3/24/2026, 1:34:48 AM
Photo
CFP hopper 1.png
Progress update
Current status: COMPLETED
Progress %100%
Planned hours
Update resource lines after submission if the plan changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
By telferfpmmmshutplanners@greatland.com.au on 3/24/2026, 2:28:20 AM
Completed
Shutdown Coordinator review
No comment recorded.
By john.rowley@greatland.com.au on 3/24/2026, 2:33:33 AM
Completed
Superintendent review
No comment recorded.
By trent.donges@greatland.com.au on 3/24/2026, 8:44:29 AM
Completed
Manager review
Approved- although sub order to be raised to determine a long-term solution.
By ethan.gardiner@greatland.com.au on 3/24/2026, 8:54:37 AM
Completed
This request is currently in COMPLETED.