Break-in Request

TBA - CV07 head chute mech Repr

+ New requestDashboard
Status
COMPLETED
Progress
100%
Hours (Planned)
18.0
hrs
Hours (Done)
18.0
hrs
Request details
Requested by
Trent Donges
Requestor email
trent.donges@greatland.com.au
WO Number
TBA
WO Title
CV07 head chute mech Repr
Area
332
Priority
High
Workgroup
GMRS/TMS/MPV/DTH
Reason
Liners on walls are quite thin. Process water inlet spigot blown through
Consequence
Will likely blow out before next shut. Will require 12-24 hrs downtime to rectify
Resources
Mech
12.0h
Impact
6.0h
Created: 3/23/2026, 7:02:12 AM
Progress update
Current status: COMPLETED
Progress %100%
Planned hours
Update resource lines after submission if the plan changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
By telferfpmmmshutplanners@greatland.com.au on 3/23/2026, 7:41:50 AM
Completed
Shutdown Coordinator review
No comment recorded.
By john.rowley@greatland.com.au on 3/23/2026, 7:59:44 AM
Completed
Superintendent review
No comment recorded.
Completed
Manager review
No comment recorded.
Completed
This request is currently in COMPLETED.