Break-in Request

16371512 - T1 Cooling Water Flow Tube

+ New requestDashboard
Status
COMPLETED
Progress
100%
Hours (Planned)
21.0
hrs
Hours (Done)
21.0
hrs
Request details
Requested by
Brenton Kelly
Requestor email
brenton.kelly@greatland.com.au
WO Number
16371512
WO Title
T1 Cooling Water Flow Tube
Area
332
Priority
Medium
Workgroup
Elec
Reason
Need this flow reading to give indication for the cooling water on the T1 Sag Mill, currently bridged in the DCS which isn't ideal.
Consequence
No indication, downtime due to high temps.
Resources
TESUEL
21.0h
Created: 3/24/2026, 5:02:25 AM
Progress update
Current status: COMPLETED
Progress %100%
Planned hours
Update resource lines after submission if the plan changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No comment recorded.
By telferfpmmmshutplanners@greatland.com.au on 3/24/2026, 6:30:35 AM
Completed
Shutdown Coordinator review
No comment recorded.
By john.rowley@greatland.com.au on 3/24/2026, 8:23:01 AM
Completed
Superintendent review
No comment recorded.
By trent.donges@greatland.com.au on 3/24/2026, 8:39:48 AM
Completed
Manager review
No comment recorded.
By ethan.gardiner@greatland.com.au on 3/24/2026, 8:52:53 AM
Completed
This request is currently in COMPLETED.