Scope expansion from 2x skirt modules to 4x, adding minimal time to job scope
Consequence
Gaps between skirt modules due to “not standard” work having been carried out prior (not installed as per drawing, 750 belt skirt rails were retrofitted previously
Resources
Mech
6.0h
Created: 3/25/2026, 9:50:19 AM
Progress update
Current status: COMPLETED
Progress %100%
Planned hours
Update resource lines after submission if the plan changes.
Approvals
Approval actions are completed from email notifications, not inside the app. This page shows the current review stage and any saved comments.
Planner review
No Parts required, will need to manage labour during the shut.
By telferfpmmmshutplanners@greatland.com.au on 3/25/2026, 3:16:16 PM
Completed
Shutdown Coordinator review
No comment recorded.
By allen.vanwyk@greatland.com.au on 3/25/2026, 6:54:35 PM